SS-PRE · Facade & Door Sample SSR-2026-ALU-06 7 min read

Thermal-Break Aluminum Windows, Facade & Doors PSI Sample Report

Inspect how SerSourcing conducts a Pre-shipment Check (SS-PRE €490) on fabricated villa window/sliding frames, curtain-wall extrusions and steel/fire doorset packages before glass crating and export container dispatch.

Open-access preview — zero email wall or newsletter spam.

Founder Technical & Procurement Review Tariff & Scope Verified: 2026-11-02
Prepared by İdris YAĞMAHAN Architect
Reviewed by Celalettin YAĞMAHAN Civil Engineer

Reviewed for technical terminology, Turkish factory field reality and published EUR scope boundaries (not statutory engineering sign-off).

Active Corporate Specimen: SSR-2026-ALU-06 · Facade & Door PSI Report
Commission This Scope on WhatsApp
SerSourcing TECHNICAL SOURCING, FACTORY AUDIT & BUYING-OFFICE DIVISION
DOCUMENT CONTROL Page 1 / 2
Document Ref.
SSR-2026-ALU-06
Tariff / Scope
SS-PRE (€490 · Up to 5 Fenestration / Door SKUs)
Issue / Revision
Rev. 02 · 2026-11-02
Classification
SPECIMEN · NDA ANONYMIZED

PRE-SHIPMENT FENESTRATION, GLAZING & STEEL DOORSET CHECK (PSI)

Product Scope: 38 × Thermal-Break Lift-Slide & Tilt-Turn Aluminum Units (RAL 7016) + 6 × Villa Steel Pivot / EI60 Technical Doors

ILLUSTRATIVE CORPORATE SPECIMEN (ZERO CLIENT DATA DISCLOSED): Client names, factory identities, heat/certificate numbers and commercial figures in this specimen are fictionalized to protect strict B2B NDA confidentiality. Scoped commercial/visual engineering record — not an accredited laboratory test certificate or statutory structural sign-off.

01 · ASSIGNMENT REGISTER & EXECUTIVE GATE SUMMARY

Commissioning Buyer Profile [REDACTED — Luxury Steel Villa Developer, Southern France]
Industrial Corridor & Travel Rule Tuzla – Pendik – Çayırova Fenestration & Extrusion Zone (Core Area)
Referenced Technical Standards EN 14351-1 Windows/Doors · EN 755-2 EN AW-6063 T6 · Qualicoat Class 2 · EN 1279 IGU
Verification Instruments & Basis Eddy-Current Non-Ferrous DFT Gauge, Digital Caliper, Diagonal Laser/Tape Check, Hardware Tally
Standard Tariff & Turnaround €490 (SS-PRE) · Target Delivery: 2 Business Days After Site Check
10 Frames + 2 Doors Sampled Units Checked
74 µm Avg. Eddy-Current Powder DFT
±1.0 mm Frame Diagonal Squareness
2 Fixes Pre-Dispatch Action Items
Executive Gate Recommendation: CONDITIONAL RELEASE — 1 HARDWARE & 1 CRATE PADDING ITEM TO CLOSE

Aluminum profile wall thickness (2.02 mm), 24 mm PA66 GF25 polyamide thermal break, RAL 7016 matte powder coating (74 µm average) and corner crimping alignment passed across 10 sampled frames. However, 2 lift-slide sash hardware boxes lacked stainless-steel coastal bogie rollers (standard zinc-plated supplied) and A-frame IGU glass crates required extra cork/foam edge blocks.

02 · SCOPED TECHNICAL OBSERVATIONS, MEASUREMENTS & COMPARISON MATRIX

Ref. Subsystem / Inspection Parameter Buyer Specification / Benchmark Recorded Field / Desk Evidence Evidence Basis Required Buyer / Supplier Gate Action
CHK-01 Extrusion Alloy Wall Thickness & Thermal-Break Strip EN AW-6063 T6, 2.0 mm main wall; 24 mm PA66+25%GF polyamide strip Offcut & unglazed frame check read 2.01–2.04 mm wall; laser-printed "PA66 GF25" stamp verified on thermal bar (not PVC). Observed / Verified Compliant; profile metallurgy & thermal barrier verified.
CHK-02 RAL 7016 Matte Architectural Powder Coating (DFT) Qualicoat >= 60 µm (Class 2 super-durable powder per coastal Villa spec) 24 eddy-current readings across mullions/sashes averaged 74 µm (range 64–86 µm); powder lot cert matched Class 2. Observed / Verified Coating thickness & batch code accepted.
CHK-03 Corner Crimping, Drainage Weep Slots & EPDM Gaskets Flush mitered corners (<0.2 mm step), vulcanized EPDM corners, capped weep slots 9/10 frames flush; W-14 sash had missing exterior drainage slot wind-caps (fitted on the spot during visit). Observed / Verified Verify weep caps across remaining lot before shrink-wrapping.
CHK-04 Insulated Glazing Units (IGU) Spacer & Temper Stamp 6 mm Tempered Solar Low-E + 16 mm Argon Warm-Edge + 44.2 Laminated, EN 12150 stamp Sampled 8 IGUs: permanent ceramic EN 12150 temper stamps & black warm-edge spacers confirmed; dimensions ±1.0 mm. Observed / Verified Accepted; ensure desiccant batch date is logged by glazier.
CHK-05 Lift-Slide Bogie Rollers & Multi-Point Lock Hardware 300 kg rated AISI 304 stainless bogie carriages + keyed-alike euro cylinders 2 opened accessory cartons contained standard zinc-plated carriages (#ZN-300) instead of coastal INOX #SS-300. Open / Hold Gate Hold dispatch until supplier swaps carriages to INOX #SS-300 with photo proof.
CHK-06 Steel Technical Doors (EI60) & A-Frame Glass Export Crates CE/fire plate affixed + ISPM-15 closed/A-frame timber crates with high-density EVA pads EI60 doors had metal ID tags & intumescent strips; glass A-frame #G-02 had bare timber touching bottom IGU edge. Open / Hold Gate Insert 15 mm high-density neoprene/EVA setting blocks under all crated IGUs.
Inspection & Sampling Basis

Scoped B2B visual field verification, random dimensional spot-sampling and documentary cross-check.

Metrology & Traceability

Field gauges zero-checked prior to measurement; heat/batch IDs cross-referenced against presented 3.1 MTCs.

Commercial Payment Gate Rule

Advance or balance wire release remains conditional upon closing all Open / Hold items logged on Sheet 2.

SerSourcing — Operated by CFY Mühendislik Mim. Dan. Yapı Malz. İnş. San. ve Tic. Ltd. Şti. · Maltepe, İstanbul SSR-2026-ALU-06 · Page 1 / 2
SerSourcing · CFY Mühendislik Mim. Dan. Yapı Malz. İnş. San. ve Tic. Ltd. Şti. CORPORATE ENGINEERING & PROCUREMENT DOSSIER — CONTINUATION SHEET
SSR-2026-ALU-06 Rev. 02 · 2026-11-02 Page 2 / 2

03 · CROSS-REFERENCED EVIDENCE & ANNEX REGISTER

ALU-A1 Logged in Dossier
Profile Cutaway, PA66 GF25 Stamp & Caliper Photo Set

Macro photographs of polyamide thermal-break knurling, wall thickness and miter joints.

DFT-B2 Logged in Dossier
Eddy-Current Non-Ferrous Coating Thickness Log

24-point micron log on anodized/powder-coated aluminum frames and steel door leaf.

GLZ-C3 Logged in Dossier
IGU Ceramic Temper Stamp & Warm-Edge Spacer Check

Close-up verification of Low-E coating orientation label and EN 12150 corner stamp.

HDW-D4 Logged in Dossier
Hardware Carton Discrepancy & Crate Padding Photos

Part-number comparison catching #ZN-300 vs #SS-300 lift-slide rollers before shipping.

04 · OPEN-ITEMS ACTION REGISTER BEFORE COMMERCIAL RELEASE

Item ID Open Technical / Commercial Point Action Owner Target Release Gate
OI-01 Exchange zinc-plated lift-slide bogie rollers (#ZN-300) for stainless coastal #SS-300 carriages across all 6 patio units. Window Fabricator Before Crate Sealing
OI-02 Fit continuous 15 mm EVA/neoprene base cushions and ratchet-strap corner blocks inside Glass A-Frames #G-01..#G-04. Packing Team Before Container Loading
OI-03 Confirm window tag codes (W-01..W-38) appear on exterior shrink-wrap so site crane crew unloads by villa floor. Fabricator QC Prior to Dispatch

05 · EVIDENCE CLASSIFICATION KEY & CORPORATE SCOPE GOVERNANCE

Observed / Verified

Directly witnessed, counted or measured on site/desk by SerSourcing within the agreed assignment window.

Document Reviewed

Recorded from supplier-submitted certificates, MTCs or drawings without assuming physical lot testing.

Supplier-Stated

Verbal or written manufacturer statement recorded transparently; requires independent verification.

Open / Hold Gate

Unresolved technical or commercial hold item recommended for closure prior to stage payment/dispatch.

Governance & Independence Standard: Issued under buyer-representation tariff SS-2026-11-V2. Zero undisclosed supplier commission. Goods contracts, product warranties, accredited EN ISO/IEC 17025 lab testing and statutory engineering sign-off remain with the respective contracting parties and appointed specialists.

06 · DOCUMENT REVISION LOG & CONTROLLED DISTRIBUTION REGISTER

Rev. Date Revision Status & QA Milestone Authorized Distribution & Archive Retention
Rev. 01 2026-10-30 Initial field / desk observation log, dimensional check sheet & annex index. Internal Engineering Desk QA Review (Maltepe HQ)
Rev. 02 2026-11-02 QA-verified corporate engineering dossier & executive gate recommendation. Commissioning Buyer (1× Encrypted PDF + Annex ZIP) · 5-Yr NDA Archive

07 · BUYER CONTRACT, PAYMENT & DISPATCH SAFEGUARD PROTOCOL

GATE-01 Proforma & Technical Specification Rider

Bind verified steel grade, coating mass, tolerances and export packing rules directly into the signed Proforma Invoice.

GATE-02 Lot-Specific Certificate & Export Pack

Verify batch-allocated EN 10204 3.1 MTC, CE DoP, packing list and draft A.TR/EUR.1 48h prior to balance wire.

GATE-03 Pre-Shipment & Loading Gate Witness

Confirm final piece count and dunnage via SS-PRE (€490) or SS-LOAD (€390) before high-security bolt seal closure.

GATE-04 Strict NDA & Zero-Commission Mandate

Issued exclusively for commissioning buyer internal governance; SerSourcing accepts zero supplier commission (0%).

Prepared By (Field / Desk Lead) Celalettin YAĞMAHAN Civil Engineer · Co-Founder
Maltepe, İstanbul · 2026-11-02
Technical Quality Review By İdris YAĞMAHAN Architect · Co-Founder
QA Control · SSR-2026-ALU-06
Corporate Verification Seal
Tariff SS-2026-11-V2 · MERSİS: 0209128951200001 · Tax ID: 2091289512 · sersourcing.com SSR-2026-ALU-06 · Page 2 / 2

Preventing Costly Window, Glazing & Villa Door Mistakes Before Export Crating

Custom architectural windows and villa entrance doors cannot be improvised on a foreign jobsite: if PVC thermal strips are substituted for PA66 GF25 polyamide, if tempered safety stamps are missing for building-control sign-off, or if glass A-frames lack elastomeric base pads, replacement lead times exceed 6 weeks.

Our architect-led Pre-shipment Check (SS-PRE €490) inspects window squareness, eddy-current coating microns, glazing build-up stamps, hardware part numbers, and export crating before final payment.

  • Verifies EN AW-6063 T6 wall gauge and genuine PA66 GF25 thermal-break strips.
  • Checks eddy-current Qualicoat / Qualanod micron readings and EN 12150 tempered glass stamps.
  • Audits lift-slide rollers, multi-point locks, EPDM gaskets and ISPM-15 A-frame glass crate cushioning.
More Corporate Deliverable Specimens

Explore Other Sector & Engineering Report Samples

SS-SAMPLE · Board & Wool Sample

Board & Wool Sample Report

Corporate sample verification & unit-area normalization dossier for fibercement boards (Betopan), moisture/fire gypsum drywall and stone-wool batts: caliper thickness, density check, m² price normalization and pallet moisture wrap.

SS-TECH · ISO 1461 HDG Sample

Scaffolding & HDG Report

Corporate technical & pre-shipment verification dossier for EN 12810/12811 ringlock/frame scaffolding, steel formwork, mezzanine floors and warehouse racking: EN ISO 1461 hot-dip galvanizing microns, rosetta weld fit-up and steel-strapped cradles.

SS-SOURCE · Solar Steel Sample

Solar Carport RFQ Report

Corporate supplier shortlist & capability screening dossier (SS-SOURCE €690) for PV solar ground-mount structures, industrial steel solar carports and aluminum roof rails: 5 factories researched, 3 verified candidates compared.

Continue Exploring
Clear Boundaries & Scope Answers

Frequently Asked Questions

We use a non-destructive eddy-current dry-film thickness (DFT) gauge calibrated for non-ferrous substrates (EN ISO 2360), allowing instant micron readings on powder-coated or anodized mullions with zero surface damage.

Fixed EUR Schedule · Free Initial Scope Review

Move your Türkiye purchase forward with a defined scope

Share your product specification, drawing or Turkish supplier details to receive a clear written scope and EUR fee confirmation before work starts.

WhatsApp Sourcing Desk