Light-Gauge Steel Villa (LGSF) Factory Audit Sample Report

Inspect how SerSourcing documents a real-world Turkish light-steel house and villa roll-forming plant visit (SS-VISIT €490 / SS-TECH €790) — separating verified coil tags and caliper measurements from unverified supplier statements before you wire a deposit.

Open-access preview — zero email wall or newsletter spam.

Founder Technical & Procurement Review Tariff & Scope Verified: 2026-11-02
Prepared by Celalettin YAĞMAHAN Civil Engineer
Reviewed by İdris YAĞMAHAN Architect

Reviewed for technical terminology, Turkish factory field reality and published EUR scope boundaries (not statutory engineering sign-off).

Active Corporate Specimen: SSR-2026-LGSF-01 · LGSF Villa Audit Report
Commission This Scope on WhatsApp
SerSourcing TECHNICAL SOURCING, FACTORY AUDIT & BUYING-OFFICE DIVISION
DOCUMENT CONTROL Page 1 / 2
Document Ref.
SSR-2026-LGSF-01
Tariff / Scope
SS-VISIT (€490) · Optional SS-TECH (€790)
Issue / Revision
Rev. 02 · 2026-11-02
Classification
SPECIMEN · NDA ANONYMIZED

SCOPED FACTORY CAPABILITY & COIL TRACEABILITY AUDIT DOSSIER

Product Scope: Cold-Formed Light-Gauge Steel Villa Framing Kit (C89 / C140 Structural Studs & Trusses — 4 Villa Units)

ILLUSTRATIVE CORPORATE SPECIMEN (ZERO CLIENT DATA DISCLOSED): Client names, factory identities, heat/certificate numbers and commercial figures in this specimen are fictionalized to protect strict B2B NDA confidentiality. Scoped commercial/visual engineering record — not an accredited laboratory test certificate or statutory structural sign-off.

01 · ASSIGNMENT REGISTER & EXECUTIVE GATE SUMMARY

Commissioning Buyer Profile [REDACTED — Residential Modular Developer, Germany / DACH]
Industrial Corridor & Travel Rule Tuzla – Gebze Industrial Corridor (Core Zone · €0 Local Road Travel)
Referenced Technical Standards EN 10346 (S350GD+Z275) · EN 1090-1/2 · Buyer Framing GA Rev.03
Verification Instruments & Basis Calibrated Digital Vernier Caliper (0.01 mm), Magnetic Coating Gauge, Visual Line Walk
Standard Tariff & Turnaround €490 (SS-VISIT) · Delivered within 2 Business Days of Site Attendance
16 Points Scoped Audit Checks
11 Verified Observed on Factory Floor
3 Reviewed Mill & QC Docs Checked
2 Hold Gates Open Pre-Deposit Items
Executive Gate Recommendation: CONDITIONAL DEPOSIT GATE — 2 OPEN ITEMS

Active CNC roll-forming lines (C89 & C140) and in-house Vertex/FrameCAD detailing station were directly observed on site. However, floor coil stock included both S350GD+Z275 and commercial DX51D+Z100 coils; Purchase Order release should require heat-number reservation for S350GD+Z275 and written confirmation of hot-dip galvanized 8.8/10.9 anchor kits.

02 · SCOPED TECHNICAL OBSERVATIONS, MEASUREMENTS & COMPARISON MATRIX

Ref. Subsystem / Inspection Parameter Buyer Specification / Benchmark Recorded Field / Desk Evidence Evidence Basis Required Buyer / Supplier Gate Action
CHK-01 CNC Roll-Forming Line & Tooling Ownership In-house C89 & C140 multi-web roll-former; zero undisclosed broker sub-contracting 2 active CNC roll-forming lines observed running C140 studs; machine serial plates match legal entity. Observed / Verified Acceptable for framing fabrication; record line allocation in PO.
CHK-02 Structural Galvanized Coil Grade & Zinc Mass EN 10346 S350GD + Z275 (min. 275 g/m² total zinc both sides) 3 slit coils on decoiler tagged S350GD+Z275 (Heat #K-4418); adjacent rack held DX51D+Z100 coils for drywall. Observed / Verified Mandate Coil Heat # linkage on packing tags prior to cutting.
CHK-03 Base Metal Thickness (BMT) vs. Total Coated Gauge 1.20 mm net BMT (±0.05 mm) on load-bearing wall studs 12-point caliper check across C140 sample run read 1.22–1.24 mm coated (~1.18 mm net BMT). Observed / Verified Within commercial sheet tolerance; repeat spot check at SS-PRE.
CHK-04 CNC Web Service Holes, Dimples & Inkjet Coding Clean swaged dimples, lip punch & readable member ID per erection drawing Inkjet profile IDs crisp and legible; minor burr noted on 38 mm MEP service punch die. Observed / Verified Request punch die dressing + protective grommets in accessory kit.
CHK-05 EN 10204 3.1 Mill Test Certificate Traceability Mill certificate matching S350GD yield (>=350 MPa) and Z275 coating Sample EN 10204 3.1 PDF reviewed for Heat #K-4418 (ReH 378 MPa, Z282 g/m²); order-specific coil not yet allocated. Document Reviewed Require order-specific 3.1 MTC submission before 2nd stage payment.
CHK-06 Shear-Wall Hold-Down Brackets & Fastener Package HDG hold-down brackets, EPDM sill tape & self-drilling screws included Sales manager verbally stated hold-downs are outsourced to a Gebze laser-cut shop; drawings not shown. Open / Hold Gate Hold deposit until sub-supplier bracket drawing & HDG spec are attached to PI.
Inspection & Sampling Basis

Scoped B2B visual field verification, random dimensional spot-sampling and documentary cross-check.

Metrology & Traceability

Field gauges zero-checked prior to measurement; heat/batch IDs cross-referenced against presented 3.1 MTCs.

Commercial Payment Gate Rule

Advance or balance wire release remains conditional upon closing all Open / Hold items logged on Sheet 2.

SerSourcing — Operated by CFY Mühendislik Mim. Dan. Yapı Malz. İnş. San. ve Tic. Ltd. Şti. · Maltepe, İstanbul SSR-2026-LGSF-01 · Page 1 / 2
SerSourcing · CFY Mühendislik Mim. Dan. Yapı Malz. İnş. San. ve Tic. Ltd. Şti. CORPORATE ENGINEERING & PROCUREMENT DOSSIER — CONTINUATION SHEET
SSR-2026-LGSF-01 Rev. 02 · 2026-11-02 Page 2 / 2

03 · CROSS-REFERENCED EVIDENCE & ANNEX REGISTER

PHOTO-A1 Logged in Dossier
CNC Roll-Former & Decoiler Bay (14 Permitted Photos)

Timestamped bay overview, profile inkjet coding close-up and decoiler coil tags.

MTC-B2 Logged in Dossier
Specimen EN 10204 3.1 Coil Certificate Log

Cross-checked chemical/yield table for Heat #K-4418 vs. EN 10346 S350GD+Z275.

MEAS-C3 Logged in Dossier
12-Point Digital Caliper & Web Geometry Sheet

Flange width (41.2 mm), web depth (140.1 mm), lip return (12.1 mm) and coated gauge log.

CORP-D4 Logged in Dossier
Trade Registry, Tax Plate & OSB Lease Verification

Confirmed operating manufacturer status matching proforma invoice issuer.

04 · OPEN-ITEMS ACTION REGISTER BEFORE COMMERCIAL RELEASE

Item ID Open Technical / Commercial Point Action Owner Target Release Gate
OI-01 Written Proforma clause locking EN 10346 S350GD+Z275 net 1.20 mm BMT (excluding DX51D substitution). Supplier / Buyer Before Advance Payment
OI-02 Detailed BOM & shop drawing for outsourced shear-wall hold-down anchors and screw coating class. Supplier Before Production Release
OI-03 Book Pre-shipment Check (SS-PRE €490) on bundled villa pallets before 40' HC container stuffing. Buyer / SerSourcing At 90% Fabrication

05 · EVIDENCE CLASSIFICATION KEY & CORPORATE SCOPE GOVERNANCE

Observed / Verified

Directly witnessed, counted or measured on site/desk by SerSourcing within the agreed assignment window.

Document Reviewed

Recorded from supplier-submitted certificates, MTCs or drawings without assuming physical lot testing.

Supplier-Stated

Verbal or written manufacturer statement recorded transparently; requires independent verification.

Open / Hold Gate

Unresolved technical or commercial hold item recommended for closure prior to stage payment/dispatch.

Governance & Independence Standard: Issued under buyer-representation tariff SS-2026-11-V2. Zero undisclosed supplier commission. Goods contracts, product warranties, accredited EN ISO/IEC 17025 lab testing and statutory engineering sign-off remain with the respective contracting parties and appointed specialists.

06 · DOCUMENT REVISION LOG & CONTROLLED DISTRIBUTION REGISTER

Rev. Date Revision Status & QA Milestone Authorized Distribution & Archive Retention
Rev. 01 2026-10-30 Initial field / desk observation log, dimensional check sheet & annex index. Internal Engineering Desk QA Review (Maltepe HQ)
Rev. 02 2026-11-02 QA-verified corporate engineering dossier & executive gate recommendation. Commissioning Buyer (1× Encrypted PDF + Annex ZIP) · 5-Yr NDA Archive

07 · BUYER CONTRACT, PAYMENT & DISPATCH SAFEGUARD PROTOCOL

GATE-01 Proforma & Technical Specification Rider

Bind verified steel grade, coating mass, tolerances and export packing rules directly into the signed Proforma Invoice.

GATE-02 Lot-Specific Certificate & Export Pack

Verify batch-allocated EN 10204 3.1 MTC, CE DoP, packing list and draft A.TR/EUR.1 48h prior to balance wire.

GATE-03 Pre-Shipment & Loading Gate Witness

Confirm final piece count and dunnage via SS-PRE (€490) or SS-LOAD (€390) before high-security bolt seal closure.

GATE-04 Strict NDA & Zero-Commission Mandate

Issued exclusively for commissioning buyer internal governance; SerSourcing accepts zero supplier commission (0%).

Prepared By (Field / Desk Lead) Celalettin YAĞMAHAN Civil Engineer · Co-Founder
Maltepe, İstanbul · 2026-11-02
Technical Quality Review By İdris YAĞMAHAN Architect · Co-Founder
QA Control · SSR-2026-LGSF-01
Corporate Verification Seal
Tariff SS-2026-11-V2 · MERSİS: 0209128951200001 · Tax ID: 2091289512 · sersourcing.com SSR-2026-LGSF-01 · Page 2 / 2

Why an LGSF Villa Factory Audit Prevents Grade Substitution

In Turkish cold-formed steel manufacturing, the single biggest hidden margin gap lies between structural S320GD / S350GD + Z275 coils and non-structural drywall DX51D + Z100 sheet. From a distance in marketing photos, both look identical as shiny galvanized C-profiles.

This corporate dossier format gives your purchasing and engineering desk verifiable floor evidence: decoiler tag photographs, digital caliper readings, CNC inkjet profile coding checks, and explicit identification of any outsourced brackets or envelope items.

  • Separates genuine roll-forming manufacturers from export brokers reselling third-party framing kits.
  • Documents coil grade tags (S350GD vs DX51D) and zinc coating class (Z275 vs Z100/Z140) directly on the shop floor.
  • Flags missing shear-wall hold-downs, chemical anchors, EPDM acoustic/sill tapes and fastener coatings before proforma sign-off.

Choosing Between Standard Factory Visit (SS-VISIT €490) and Technical Review (SS-TECH €790)

Select SS-VISIT (€490) when you need physical existence, roll-forming machine verification, floor activity, and core coil/packing observation within up to 4 hours on site. Upgrade to SS-TECH (€790) when you have up to 10 structural framing drawings and up to 50 pages of BOM/mill schedules requiring a 6-hour clause-by-clause engineering review.

More Corporate Deliverable Specimens

Explore Other Sector & Engineering Report Samples

SS-TECH · Modular Cabin Sample

Prefab Cabin Tech Report

Technical factory review specimen for flat-pack modular cabins, site camps and prefabricated homes: chassis welding jigs, PIR/EPS sandwich wall press, roof gutter drainage and flat-pack stacking.

SS-PRE · EN 1090 Hangar Sample

Steel Hangar PSI Report

Pre-shipment inspection (PSI) corporate dossier for EN 1090 heavy structural steel warehouses, industrial factory buildings and aircraft/logistics hangars: 3.1 heat numbers, Sa 2½ blast, DFT microns and end-plate hole pitch.

SS-LOAD · Container CLS Sample

Panel Loading CLS Report

Container & mega-trailer loading supervision (CLS) corporate dossier for PIR/rockwool sandwich panels, flashings and steel purlins: empty container light/moisture check, 11.80 m bundle protection, ISPM-15 dunnage and bolt-seal log.

Continue Exploring
Clear Boundaries & Scope Answers

Frequently Asked Questions

Yes. Click the "Export / Print Corporate A4 PDF" button above to generate a clean, multi-page corporate engineering PDF directly in your browser with zero email forms or lead walls.

Fixed EUR Schedule · Free Initial Scope Review

Move your Türkiye purchase forward with a defined scope

Share your product specification, drawing or Turkish supplier details to receive a clear written scope and EUR fee confirmation before work starts.

WhatsApp Sourcing Desk